After conclusion of the basement excavation work, a blinding layer was inserted. At a later stage, the tower ring foundation was bolted to this basket anchor.
We worked until late in the evening in order to guarantee completion within the deadline.
Each foundation was filled with hundreds of cubic metres of concrete.
The cast ring foundation weighing some 30 tonnes on which the tower was mounted. The air gap between the cast ring and the foundation concrete was closed with so-called grouting.
Excavation for the transformer station next to the foundation.
Each facility has its own transformer. From here, the energy is transmitted to the transfer station and from there to the Mattersburg substation, where the energy is fed into the public grid.
Overall, hundreds of kilometres of cable were laid.
The 600 tonne crane for the construction of the facility was delivered.
The 600 tonne crane was assembled.
When assembled, the crane was 110 m high.
The first facility was delivered.