Delivery of the first parts of the plant to the transfer point in the valley.
Transport of the first blade via Ratten.
Nerves frayed as the first curves were negotiated.
90 ascents of the mountains were necessary to transport all the components of the facility onto the mountain. Ultimately, the lorry drivers only required a further 50 minutes.
The first of four tower elements of the first constructed facility.
Transfer and anchoring to the threaded bolts of the basket anchor.
Hoisting of the fourth and last tower elements. The star of the rotor blades is already pre-assembled.
Setting down of the 45 tonne turbine hall.
Assemble of the 27 tonne rotor.
The first facility was built - 9 further ones to follow.
The Steinriegel wind farm was completed in only 9 weeks.
The 500 tonnes crane with a deadweight of 90 tonnes scaled a mountain to the plants to be built.